A BILL TO BE ENTITLED
AN ACT TO change the property tax exclusion for solar energy electric systems, TO PROHIBIT THE CONSTRUCTION OF new UTILITY‑SCALE SOLAR FACILITIES THAT ARE NOT QUALIFYING FACILITIES UNDER PURPA, AND TO REQUIRE FINANCIAL ASSURANCE FOR EXISTING SOLAR ENERGY FACILITIES.
The General Assembly of North Carolina enacts:
SECTION 1.(a) G.S. 105‑275(45) reads as rewritten:
"§ 105‑275. Property classified and excluded from the tax base.
The following classes of property are designated special classes under Article V, Sec. 2(2), of the North Carolina Constitution and are excluded from tax:
…
(45) Eighty percent (80%) Forty
percent (40%) of the appraised value of a solar energy electric system. For
purposes of this subdivision, the term "solar energy electric system"
means all equipment used directly and exclusively for the conversion of solar
energy to electricity."
SECTION 1.(b) This section becomes effective July 1, 2025, and applies to taxes imposed for taxable years beginning on or after that date.
SECTION 2.(a) G.S. 62‑110.1 is amended by adding a new subsection to read:
"(a1) The Commission shall not issue a certificate of public convenience and necessity for a utility‑scale solar project, as defined in G.S. 130A‑309.240(a)(6), that is not a qualifying small power production facility under the federal Public Utility Regulatory Policy Act, as defined in 18 C.F.R. § 292.203(a), unless the utility‑scale solar project is to be sited on property meeting any of the following criteria:
(1) The property is a brownfields property as defined in G.S. 130A‑310.31, and the developer of the project enters into a brownfields agreement with the Department of Environmental Quality pursuant to G.S. 130A‑310.32.
(2) The property is not currently being used for agricultural or horticultural production.
(3) The property is timberland that has been clear‑cut harvested and is not in production at the time of application."
SECTION 2.(b) This section is effective when it becomes law and applies to applications for a certificate of public convenience and necessity for a utility‑scale solar project received on or after that date.
SECTION 3. Section 4 of S.L. 2023‑58 reads as rewritten:
"SECTION 4. This act becomes effective as follows:
(1) Section 2(a) of this act is effective when it becomes law, except as follows:
a. The requirements for decommissioning and registration established under G.S. 130A‑309.240(b) and (e), respectively, as enacted by Section 2(a) of this act, become effective November 1, 2025, and apply to utility‑scale solar projects constructed prior to or after that date. The owner of a utility‑scale solar project shall register with the Department as follows: (i) by November 1, 2025, or at least 90 days prior to the commencement of construction of the project if the project is constructed after November 1, 2025; and (ii) at least 90 days prior to commencement of rebuild or expansion of a utility‑scale solar project.
b. The requirements for
submittal of a decommissioning plan and financial assurance established under
G.S. 130A‑309.240(c) and (d), respectively, as enacted by Section
2(a) of this act, become effective November 1, 2025, December 1,
2026, and shall only apply to (i) utility‑scale solar
projects for which applications for certificates of public convenience and
necessity are pending or submitted on or after the effective date of this act
and (ii) utility‑scale solar projects that are generating solar energy or
are interconnected to a transmission facility on the date this act becomes
effective, only if the project is rebuilt or expanded, as those terms are
defined by G.S. 130A‑309.240(a)(2) and (a)(4), after the effective
date of this act, in which case the project shall be subject to the
requirements of G.S. 130A‑309.240(c) and (d). utility‑scale
solar projects constructed prior to or after that date. The owner of a
utility‑scale solar project shall submit a decommissioning plan and
establish financial assurance (i) by November 1, 2025, or prior to
commencement of construction of the project if the project is constructed after
November 1, 2025, and (ii) prior to commencement of rebuild or expansion of a
utility‑scale solar project.by December 1, 2026.
(2) The remainder of this act is effective when it becomes law."
SECTION 4. Except as otherwise provided, this act is effective when it becomes law.