162A-213. Time for collection of system development fees.

(a) Land Subdivision. - For new development involving the subdivision of land, the system development fee shall be collected by a local governmental unit at the later of either of the following:

a. The time of plat recordation.

b. When water or sewer service is committed by the local governmental unit.

(b) Other New Development. - For all other new development, the local governmental unit shall collect the system development fee at the earlier of either of the following:

a. The time of application for connection of the individual unit of development to the service or facilities.

b. When water or sewer service is committed by the local governmental unit. (2017-138, s. 1; 2018-34, s. 3(a).)